In brief
MRP stands for material requirements planning: based on orders, forecasts, bills of materials and stock levels, it calculates which material is needed in what quantity and by when, to be purchased or produced.
How material requirements planning works
The logic is simpler than the name suggests. The starting point is the demand for finished products from orders and forecasts. Using the bill of materials, it is broken down level by level into the demand for subassemblies and material. The planning then subtracts stock on hand and quantities already ordered. What’s left is the net requirement.
Then lead times come into play: if the supplier needs two weeks and the subassembly three days in the workshop, the purchase order has to go out correspondingly earlier. The result is scheduled suggestions for purchase and manufacturing orders.
MRP I and MRP II – the difference
Classic material requirements planning, today often called MRP I, spread from the 1960s onward, when computers could first calculate such BOM explosions in a reasonable time. It was shaped above all by Joseph Orlicky, whose book “Material Requirements Planning” was published in 1975. MRP I plans only material and assumes unlimited capacity.
MRP II stands for manufacturing resource planning and extends the approach to the other resources: machine and staff capacity, the production program, shop floor control and the link to finance. Today’s ERP systems later grew out of these systems. When people talk about MRP software today, they usually mean this extended form.
When MRP pays off for SMEs
Material requirements planning pays off as soon as you make products from several components, need material with longer delivery times or have several orders competing for the same machines. If the workshop is regularly waiting for missing parts, it’s high time.
The benefit shows on two sides: fewer missing parts in the workshop and less money tied up in material kept in stock. Especially in one-off and small-batch production, which many trade businesses know well, the art lies in procuring exactly what the actual orders need – no more and no later.
The prerequisite is reliable data: current bills of materials, correct stock levels from inventory management and realistic delivery times. If these are off, even the best system will reliably calculate the wrong result.
MRP in Odoo
Odoo itself lists its production app under the name “Manufacturing (MRP)”; see Odoo Manufacturing. The app connects bills of materials, work centers and manufacturing orders with Inventory and Purchase. You control replenishment through reordering rules or make-to-order procurement. For medium-term planning there is the Master Production Schedule (MPS), which turns forecasts and actual demand into replenishment suggestions that you review and launch.
Because everything lives in one system, quality checks and the maintenance of machines are part of it too. That way production sees test results and maintenance dates in the same place as its orders.
Frequently asked questions about MRP
Your question isn’t here? Ask us directly – the initial consultation is free and without obligation.
Is MRP the same as ERP?
No. MRP plans material and production, while an ERP system also covers sales, accounting, HR and more. Historically, MRP II is considered the forerunner of ERP, and in modern ERP systems like Odoo the MRP function is one part of the whole.
What is the difference between MRP I and MRP II?
MRP I calculates only material requirements. MRP II (manufacturing resource planning) also takes into account machine and staff capacity, production planning and finance.
Do we need separate software for MRP?
Not necessarily. If inventory, purchasing and sales already run in the ERP, that’s the best place for material requirements planning, because it accesses the same stock levels and orders. In Odoo, that’s the Manufacturing app.